Southern Cross, Newtown
Project: Refurbishment
Address: 90 Hanson Street, Newtown
Contractor: Fletchers
Year: 2013-2014
Timeframe: 12 Months
Description: Upgrade existing building
St Pats College, Silverstream
Project: New build
Address: Ferguson Drive, Silverstream
Contractor: Maycroft
Year: 2013-2014
Timeframe: 12 Months
Description: New gymnasium & sports hub
Westpac Stadium
Project: New Build Mezzanine Bar
Address: Aotea Quay, Wellington
Contractor: Hawkins Construction
Year: 2013-2014
Timeframe: 6 Months
Description: New build mezzanine floor to accommodate new bar.
Central Park Flats
Project: WCC Housing Upgrade
Address: Nairn Street, Brooklyn, Wellington
Contractor: L T McGuinness
Year: 2010-2012
Timeframe: 24 Months
Description: This project involved the refurbishment of 220 council flats in three blocks. All flats were re-configured and completely re-plumbed.
Willis Central
Project: Two Tower office block development for the Wellington company
Address: Willis & Boulcott Streets, Wellington
Contractor: Hawkins Construction
Year: 2009-2011
Timeframe: 24 Months
Description: A Green Star office development incorporating storm water reuse, solar domestic hot water preheating and partial use of HDPE. It also included the use of the Akavent system for some of the soil stacks.
Pipitea Plaza, Wellington
Project: 10 Storey Office Development for Government Communications Security Bureau
Address: Pipitea Street, Wellington
Contractor: Naylor Love Construction
Year: 2008-2010
Timeframe: 24 Months
Description: This Green Star development included an extensive Solar DHW System, Siphonic Storm Water System capturing water for reuse for toilet flushing and use of MDPE for all waste and storm water pipe work.
Victoria University Student Accommodation
Project: 240 Room Student Accommodation
Address: Fairlie Terrace, Wellington
Contractor: Hawkins Construction Ltd
Year: 2008-2009
Timeframe: 12 Months
Description: John Leen Plumbing Ltd completed the plumbing/drainage and gas installation for three towers of student accommodation in this 240 room development consisting of ensuite rooms and common area bathrooms.
Shamrock House, Thorndon
Project: Seismic Upgrade
Address: 81-83 Molesworth Street, Thorndon, Wellington
Contractor: Keyway Construction
Year: 2014
Timeframe: 6 Months
Description: Refurbishment
University of Christchurch – Waimare Village
Project: Temporary Student Accommodation
Address: Waimare Road, Avonhead, Christchurch
Contractor: Hawkins
Year: 2014
Timeframe: 3 Months
Description: New build student accommodation